DEVELOPMENT OF MOND, KAKI AND BUSHGAN OIL FIELDS

Project activities in three fields (Mond, Kaki and Bushgan):

  • Three-dimensional seismic operations as well as the seismic lateral SVSL Mond and repair operations completed drilling well No. 6 and No. 8 Mond field verification layer 's upper and lower layers Sarvak Mond.
  • Design and installation of the pumps heavy oil well (pump (PCP doing successful test operation of the pump in Well No. 6 and 8 field Mond.
  • South Road Mond field length 22/5 km and a width of 7 meters.
  • Prepare a comprehensive plan to develop three fields (Mond, Kaki and Bushgan).
  • Signature HOA between Inter Naft Gas Prom Pars Company (INGP) and National Iranian Oil Company (NIOC) for the three fields (Mond,kaki and Bushgan).
  • Check out the technical / Legal and Finance negotiations,(Service Contract) to develop three fields with National Iranian Oil Company (NIOC).

 

Project activities planned three fields (Mond, Kaki and Bushgan):

  • Sort of an early production of 7000 barrels / day after 38 months from the effective date of the contract.
  • First phase production rate of 10,000 barrels / day after 49 months from the effective date of the contract.
  • Increased production of early phase sort 14,000 barrels / day after 58 months from the date of contract.
  • The second phase to produce 26 thousand barrels / day after 77 months from the date of contract.

Contractors:

Inter Naft Gas Prom Pars Company (INGP) - to develop and integrate the three fields method Buy Back.

 

Geographical location of the project:

Mond: is located 80 kilometers southeast of Bushehr.

Kaki: Located 80 kilometers southeast of Bushehr, 15 kilometers south of the North East Mond is Khormoj.

Bushgan: Located about 100 km south-west of Shiraz and is 100 km from Bushehr.


 

DEVELOPMENT OF ZAGEH OIL FIELD

 

Contractors:

INTER NAFT GAS PROM PARS COMPANY (INGP).

 

Geographical location of the project:

Slums: 6 km north of the coast of the Persian Gulf, 30 km southeast of Port Deilam under the edge of the Rag Sefid Oil Field.

 

Heavy oil field activities in slum:

  • Implementation of three-dimensional seismic survey vessel, together with the Rag Sefid Oil Field. 
  • Harvest operations, data processing and data interpretation.
  • PSTM and PSDM processing operations.
  • Signature HOA between Inter Naft Gas Prom Pars Company (INGP) and National Iranian  Oil Company (NIOC) for the evaluation phase field method slum EPCF.
  • Improvement of about 40% in the preparation and construction of access roads and drilling well No. 2 Camp Slums.

 

Heavy oil field activities planned in slums:

The assessment phase include:

  • Conducting negotiations for finalizing the assessment phase contract between Inter Naft Gas Prom Pars Company (INGP) and  National Iranian Oil Company (NIOC)  method EPCF.
  • Completion of the construction of access roads to well # -2 slums.
  • Drilling wells for collecting the data, and finally 2: Slums of production wells Pabdeh or Sarvak.
  • Construction of the process plant and pipeline to transport oil from wellhead production wells to start production from the field of operation.
  • Preparation of a comprehensive development plan (MDP) after data collection and study of static and dynamic.